Days 33-35

We have mostly been unpacking and organizing stuff over the past few days. We also puttied, sanded, and stained the beam between the kitchen and living room:

AND the fence people came out and tore out the old chain link fence and started installing the new privacy fence! Can’t wait for them to finish (maybe Saturday?)! https://www.linkedin.com/company/quintessential-fence-contractors

AND Ernesto helped us frame in what used to be the door from the kitchen to the deck and stuccoed the outside. Next week we should get in our new sliding glass doors to replace what is currently the double window next to the fridge. Can’t wait!

Brian has removed all the old shutters and we will be getting the windows cleaned soon.

On the building plan front….our engineer has asked to have 1 more day to finish them. He is now a couple of weeks past the original date he told us…HOPEFULLY we will have them tomorrow.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s